Construction Updates - Sam Houston State University Physical Plant          

SAM HOUSTON STATE UNIVERSITY
Physical Plant Department
Construction Project Highlights
March 2008

 

  COMPLETED PROJECTS                

 

PROJECTS IN PROGRESS:

   

COLLEGE OF HUMANITIES & SOCIAL SCIENCES
Status:  Under Construction

Programmed Amount:  $30,000,000
Source of Funds:  TSUS Revenue Bonds
Start Date:  May 14, 2007
Substantial Completion Date:  
November 2008
Departments Effected: 
SAM Center, Teaching Enhancement, College of Humanities and Social Sciences, Sociology, Psychology, Philosophy, Political Science, Payroll, Human Resources, Purchasing, Business Office, Accounts Payable.

 

 

 

CARD ACCESS PHASE II
Status:  In Development

Programmed Amount: $750,000.00
Source of Funds: 
Designated Tuition Fund Balance.
Start Date: April 4, 2008
Substantial Completion Date:  January 29, 2009
Buildings Effected:  Bobby K. Marks Administration Building, Farrington Building, Estill Office Building, Academic Building IV, Evans Complex, Thomason Building, Academic Building II, Academic Building I, Smith-Hutson including Addition, Newton Gresham Library, George J. Beto Criminal Justice Center, Teacher Education Center, University Theater Center, Dan Rather Communications Building, Health and Kinesiology Center, Lee Drain Building, School of Music Building, Chemistry and Forensic Science, and Counselor Education Building.

 

 

 

PERFORMING ARTS CENTER
Status:  In Design

 

Renderings Courtesy of WHR Architects

Programmed Amount: $35,000,000
Source of Funds: 
TSUS System Bonds
Start Date: June 2008
Substantial Completion Date:  December 2009
Buildings Effected:  None 

 

 

 

BOWERS STADIUM PRESSBOX ELEVATOR
Status:  In Development
 

 

Programmed Amount: $1,350,000
Source of Funds: 
Designated Tuition Fund Balance
Start Date: May 2008
Substantial Completion Date:  November 2008
Buildings Effected:  Bowers Stadium Press Box

 

 

 

RELOCATION OF THE UNIVERSITY'S TELECOMMUNICATION OPERATIONS
Status:  Under Construction
 

Programmed Amount: $4,200,000
Source of Funds: 
Cash on Hand.
Start Date: July 2008
Buildings Effected:  Telephone Services, AB I